Building Permit in Phuket Property: Buyer Checklist Before Deposit
This is a narrow legal-operational guide. It is not a generic Thailand property due diligence checklist. The question here is simple: when a developer says “the building permit is ready” or “the permit is in process”, what should a foreign buyer do before wiring money?
The answer is not to ask for one PDF and move on. The permit has to be read against the title deed, approved plans, EIA position, condominium registration path, payment schedule and SPA guide for Thailand property. In Phuket, where many projects are sold off-plan and often launched early, the gap between sales material and permitted design is where buyers get hurt.
| Permit milestone | Typical timing | What buyers verify |
|---|---|---|
| Pre-sales marketing | 6-18 months before permit | Brochure vs approved scope |
| Permit issued | Before major construction | Plot, floors, unit count match SPA |
| EIA clearance (if required) | Often 12-24 months pre-handover | Drainage, height, parking |
| Condominium registration | Post-completion | Foreign 49% quota path |
| Handover | 30-90 days after completion | Snagging + common areas |
| Foreign quota check | Before deposit | 49% ceiling per building |
The statutes behind the permit
Three pieces of legislation decide whether a Phuket project may lawfully be built, and knowing which is which saves a great deal of confusion when a developer’s answer covers only one of them.
The Building Control Act B.E. 2522 (1979) is the source of the permit itself. It governs approval of the structure against the submitted plans, and it is administered locally, which on this island means the relevant municipality or sub-district administration rather than a national office.
The environmental impact regime sits alongside it and is separate. It engages once a residential project reaches roughly 80 units or 4,000 sqm of usable area, and an approval under it is a precondition rather than a formality. A project can hold a building permit and still be waiting on this.
The Condominium Act B.E. 2522 (1979) is the third, and it governs whether the finished building can be registered as a condominium at all, which is what makes unit titles and the 49% foreign quota possible. A building under construction with valid permits may still not be registered, and until it is, no unit deed exists to transfer to you.
The practical consequence is that “we have permits” answers one of three questions. Ask about all three by name, and ask for dates on each.
What a building permit actually proves
For a buyer, the permit matters because it is one of the documents that turns a sales promise into a legally traceable project. If the brochure says eight floors, a rooftop pool, underground parking and a certain unit layout, the buyer needs to know whether the approved construction documents support that story. If the permit describes a different building, a smaller building, a different structure or an earlier design, the buyer has a question that should be answered before deposit.
The permit also helps test whether the project timeline is credible. A developer can market before every process is finished. That is not automatically wrong. Early-stage buying is common in Phuket and can be attractive when pricing is right. But if construction milestones, payment calls or promised handover dates depend on a permit that is not issued or not aligned with the final design, the buyer is taking a risk that should be reflected in the contract.
| Buyer question | What the permit helps verify | What it does not verify |
|---|---|---|
| Can this building legally be built as described? | Approved construction scope, land plot, building type and design basics | Developer finances or delivery discipline |
| Does the project match the sales floor plan? | Building parameters, floors, unit mix and common areas | Interior quality or furniture package |
| Can payments be tied to construction progress? | Whether construction milestones are based on permitted work | Whether milestones are fair to the buyer |
| Does EIA still matter? | Whether the construction approval fits the approval chain | Whether EIA conditions are fully satisfied |
| Can the condo be registered later? | Part of the document trail for lawful construction | Final juristic person registration or foreign quota |
Good developers can explain this cleanly. They do not treat permit questions as hostile. They know serious buyers, lawyers and resale purchasers will ask the same thing.
What the permit does not prove
A building permit does not prove that the seller owns the land free of encumbrances. You still need a title search in Thailand and confirmation of seller authority. It does not prove that a condominium unit is available in foreign freehold. That is a separate Condominium Act and foreign quota question. It does not prove that the developer can finance construction through completion. It does not make bad SPA clauses safe. It does not guarantee rental performance, view preservation, common area completion or furniture delivery.
It also does not always prove that the current sales plan is the final approved plan. Projects evolve. A developer may amend layouts, redesign common areas, combine units, adjust parking or revise building systems. Some changes are minor. Some affect value. If your specific unit, floor, view, terrace, parking or common facility is important, the permit and approved plans need to be checked against what you are actually buying.
The most dangerous phrase is “standard procedure”. Buyers hear it when a document is missing, delayed or hard to explain. Standard procedure for whom? The developer may be comfortable managing permit risk because it controls the project. The foreign buyer does not control it. Your protection is the reservation wording, legal review period, refund language and SPA structure.
This is why the permit check should sit inside a broader legal guide to buying property in Thailand, not as a standalone tick box. The permit answers one part of the transaction. The deal is safe only when the document chain is coherent.
How building permit, EIA, condo registration and SPA connect
Two thresholds decide whether the EIA question arises at all, and they are worth knowing before you ask the developer about it. Residential projects in Thailand generally fall inside the environmental impact assessment regime once they reach 80 units, or once total usable area reaches 4,000 sqm, whichever comes first. Below those figures a project may proceed without one; above them it may not. Confirm the current thresholds and how they apply to a specific project with your lawyer, because the categories are revised from time to time and a project close to a threshold is exactly where a developer’s answer deserves checking.
Phuket adds its own layer on top. The island carries elevation-based building restrictions that do not exist in most of Thailand: construction is prohibited above a defined contour on the hillsides, and height limits step down as you approach the coast, with the tightest limits applying nearest the beach. A hillside project’s permit is therefore doing more work than a permit on flat land, and a plan that quietly exceeds a height limit is not a plan that can be built.
If the project requires EIA approval in Phuket property, the building permit should not be reviewed in isolation. EIA conditions may affect drainage, access, height, parking, waste systems or common areas. If the developer says EIA is pending but the building permit exists, the lawyer should understand how the authority process is structured for that project. If the developer says EIA is not required, the lawyer should check why.
Condominium registration is another separate step. A building can be under construction with permits and still not yet be registered as a condominium. For a foreign buyer, final condominium registration matters because it supports unit title transfer and foreign quota allocation. The buyer should know whether the SPA makes payments conditional on legal milestones or only on calendar dates. Calendar dates can be dangerous if the legal process is not moving at the same speed.
The SPA should carry the risk allocation. If the permit is already issued and matches the plans, the SPA should attach or reference accurate floor plans, specifications and delivery obligations. If the permit is pending, amended or conditional, the SPA should say what happens if approval is refused, delayed or granted in a form that materially changes the project. Without that language, the buyer may have paid into uncertainty with limited leverage.
For off-plan purchases, read this alongside the off-plan property Phuket guide and mistakes foreigners make choosing projects. Permit risk is not the only risk, but it is one of the risks that should be resolved before large payments begin.
Permit dates and what they mean for your timeline
A building permit is not open-ended. Thai practice issues permits with a limited validity, typically around 1 year for the commencement of works, with extensions available on application. That matters to a buyer in two specific ways.
First, an issued permit is not the same as an active one. A permit granted 3 years ago on a project where nothing has been built may have lapsed, and re-application means re-approval under whatever rules apply now rather than the rules that applied then. Ask for the issue date, not just confirmation that a permit exists.
Second, an amended permit resets some of your assumptions. Developers commonly amend permits as designs evolve, and an amendment is a legitimate part of building. What is not legitimate is a sales plan that reflects one design and a permit that reflects another. Ask which version of the approved plans your unit appears in, and have your lawyer compare the permit drawings against the floor plan attached to your contract.
| Question to ask | Why it matters | What a clean answer looks like |
|---|---|---|
| Permit issue date | Permits lapse if works do not commence | A date, plus evidence works began within the validity period |
| Amendments since issue | Your unit may sit in a superseded version | The amendment history, with dates |
| Approved plans versus sales plans | The two diverge more often than buyers expect | Permit drawings compared against your contract annex by your lawyer |
| EIA status against the 80-unit and 4,000 sqm thresholds | Determines whether approval is required at all | Either an approval, dated, or a documented reason none is needed |
| Height and elevation compliance | Phuket restricts both, and hillside plots most of all | Confirmation the approved height sits inside the applicable limit |
Buyer checklist before paying a deposit
- Has the building permit been issued? If yes, ask for the permit reference, date and relevant approved-plan summary. If no, ask the expected timeline and what deposit protection applies while it is pending.
- Which land plot and building does the permit cover? The document should connect to the land and project you are buying, not only to the developer group.
- Does the permit match the sales floor plan? Unit size, floor, building location, balcony, parking and common areas should not conflict with approved plans.
- Has the design changed since permit approval? If yes, ask whether amendment approval is needed or already obtained.
- How does the permit relate to EIA status? The answer should be project-specific, not a slogan.
- Are payments tied to construction stages or dates? If payments are due before permit risk is closed, the buyer is funding uncertainty.
- What does the reservation form say about legal review? You need time for a lawyer to check documents before the deposit becomes non-refundable.
- What does the SPA say if permit issues delay handover? Delay penalties, refund rights and termination mechanics should be written.
This is not paperwork for paperwork’s sake. These questions protect your deposit. A buyer who asks after signing has weaker leverage than a buyer who asks before transferring funds.
Do not wire first and review later
We help buyers request the right documents before the sales deadline, then compare the legal answer with the commercial deal.
Buyer scenarios: what to do with each permit answer
Scenario 2: Permit issued, but plans differ from sales material. Stop and ask why. Sometimes the sales deck is outdated. Sometimes the approved plans changed. Sometimes the difference is minor. Sometimes your view, balcony, layout or common facility has changed. Your lawyer should get a written explanation before you sign.
Scenario 3: Permit pending, launch pricing available now. This is common in early off-plan deals. It can be acceptable only when the deposit is small, refundable after legal review, and payment milestones do not force major funds before the legal path is clear. If the developer wants a large non-refundable deposit while permit status is unresolved, slow down.
Scenario 4: Permit amendment in process. Ask what changed. A minor technical amendment is different from a change in floor count, building height, access, parking or unit configuration. The SPA should protect you if the amendment materially changes what you bought.
Scenario 5: Developer will not share permit details. Treat this as a red flag. There may be innocent reasons, but you do not need to guess. If the sales team cannot provide enough for a lawyer to verify status, do not let urgency become the reason you accept poor information.
Scenario 6: Resale condo in an already completed building. The permit question is usually less central than title, foreign quota, juristic accounts, building condition and transfer documents. Still, if the building has unauthorized extensions, rooftop additions or converted common areas, permit history can become relevant.
Red flags that should slow the deal down
Red flags include:
- The sales team says the permit exists but cannot provide any reference or document route for lawyer review.
- The developer says construction has started while permit status is unclear.
- The reservation form makes the deposit non-refundable before document review.
- The approved plan appears to show different floors, unit sizes, access or common areas from the brochure.
- The SPA allows broad plan changes without buyer consent or refund rights.
- Payment milestones are calendar-based even if legal approvals are unresolved.
- The developer discourages independent legal review or pushes an in-house lawyer only.
- EIA, building permit and condominium registration answers conflict with each other.
- The unit is sold as foreign freehold, but foreign quota confirmation is not available.
One red flag is a question. Several together are a pattern. The buyer’s job is not to solve the developer’s document process. The buyer’s job is to decide whether the risk is acceptable before money is locked.
Decision framework for foreign buyers
First, is the permit issued, pending, amended or not required for the transaction type? Second, does the permit position match the specific building and unit being sold? Third, do the other legal documents support the same story: title, EIA, foreign quota, floor plans and draft SPA? Fourth, if something changes, does the contract protect your deposit and future payments?
If all four answers are clean, the building permit should not block the purchase. If one answer is unclear, ask for documents and a written lawyer note. If two answers are unclear, do not pay a non-refundable deposit. If the developer refuses to document the permit position, compare other options in the Phuket projects catalogue before accepting the risk.
The commercial lens matters too. A launch discount can compensate for some early-stage risk if the contract is fair. It cannot compensate for a contract that makes the buyer carry all legal uncertainty. A ready-to-transfer resale unit may cost more per square metre, but the document risk can be lower. A buyer choosing between those two should price risk, not just price the unit.
For a first-time buyer, use the broader buying property in Phuket guide to understand the purchase process. Then use this permit checklist when the project reaches reservation stage.
What to put in the SPA?
If the permit is pending or amendment approval is needed, the SPA should be more careful. Your lawyer may request clauses covering approval deadlines, delayed payment triggers, refund rights, buyer termination rights, revised-plan consent, late delivery penalties and what happens if the final approved design materially differs from the sales package.
Do not rely on a WhatsApp promise that “nothing will change”. If nothing will change, the developer should be comfortable putting the principle into the SPA. If the developer cannot, you should assume the contract, not the chat, will control the outcome.
Also check exhibits. Floor plans, furniture packages, finish schedules, parking rights, storage, branded residence benefits and common facilities should be attached or clearly referenced. A permit may authorize a building, but the SPA defines what you are buying inside it.
Final checklist before deposit
- I know whether the building permit has been issued, is pending, is being amended or is not relevant.
- My lawyer has enough information to verify the permit against the land and project.
- The permitted design does not conflict with the unit plan, building location, floor, area or common facilities I am buying.
- EIA status and building permit status make sense together.
- The reservation agreement gives a legal review period before the deposit becomes non-refundable.
- The SPA will protect me if permit issues delay handover or change the unit materially.
- Foreign quota, title and seller authority are being checked separately.
- I have not treated the permit as a substitute for full due diligence.
That is the practical standard. You do not need to become a permit specialist. You do need to make sure the legal construction story matches the commercial story before you fund it.
Frequently Asked Questions
A building permit shows that the local authority approved construction for a defined building on a defined land plot under stated specifications. It does not prove foreign quota, title quality, developer solvency or buyer-friendly SPA terms.
Yes. For off-plan condos, villas and resort residences, ask for building permit status before a deposit becomes non-refundable, especially if construction has started or payment milestones are tied to construction progress.
No. EIA approval deals with environmental and planning impact for projects that require it. A building permit authorizes construction details. Both may matter, and they should match the same project design.
Yes. The permit may not match the sales floor plan, EIA conditions may still affect the project, condominium registration may be pending, or the SPA may let the developer change material details.
A Thai property lawyer normally reviews the permit against title documents, EIA status, floor plans, unit specifications and the draft SPA. Technical review may also involve an engineer for complex buildings.
Pending is not always a deal breaker, but it must be priced and contracted as risk. Use refundable reservation language, delay protections and payment milestones that do not force you to fund unresolved permit risk.
Maksim Shchegolev
Founder, MORE Group
Founder of MORE Group. Four years in investment banking before moving to Phuket, where he has worked in the local property market since 2018. Oversees developer relationships and every engagement above $300K.
About MORE Group →Get a Focused Phuket Property Shortlist
Share budget, area and goal. We will reply with suitable live projects, not a generic catalogue.